Sylvania ends Thaba JV partnership after mining performance falls short
Persistent ore supply problems, lower feed grades and rising mining costs have prompted Sylvania Platinum to terminate its joint venture with ChromTech subsidiary Limberg Mining Company. The company, however, intends to keep processing operations running using historical chrome tailings
Sylvania Platinum has invoked the termination clause in its Thaba Joint Venture (JV) agreement with Limberg Mining Company (LMC), a subsidiary of ChromTech Mining Company, after continued underperformance in mining operations made it difficult for the partnership to meet its operational and investment targets.
The termination follows ongoing challenges with the supply of run-of-mine (ROM) ore to the Thaba operation in Limpopo. Under the agreement, LMC was responsible for mining and supplying ROM ore and historical chrome tailings, while Sylvania Metals managed the chrome and platinum group metals (PGM) processing plants.
However, since commissioning, mining activities have consistently delivered lower-than-expected ROM ore volumes and feed grades for both chrome and PGMs. Mining costs have also been significantly higher than planned, adding further pressure to the operation.
Sylvania says it engaged with LMC to address the production challenges and establish revised operating arrangements that would allow the JV to continue while meeting the required investment parameters. However, the parties failed to reach an agreement.
The company has therefore exercised its contractual right to terminate the partnership, with the termination taking effect on December 24, 2026, following the 20-business-day notice period issued on 25 November.
Processing operations to continue
Although the mining partnership is coming to an end, Sylvania is looking at ways to maintain processing activities at the site.
The company has an option to continue treating historical tailings from the site’s tailings storage facility (TSF), as well as future tailings generated by LMC. It also intends to enter into a Use and Access agreement with LMC to continue operating relevant sections of the processing plant.
According to Sylvania, historical TSF tailings alone are expected to provide sufficient feed material to sustain on-site processing operations for approximately four to four-and-a-half years. This period could be extended depending on LMC’s future mining activities and the availability of additional tailings.
The Thaba processing operation is also expected to become part of Sylvania’s existing Sylvania Dump Operations (SDO), with its current management structure, technical support and operational oversight remaining in place.
This means the termination will change the way the Thaba operation sources and processes material rather than necessarily bringing processing activities to an immediate halt.